Activities for the Week of September 4-8

PowerTel

  • PowerTel will commence work September 5th with a full crew compliment.
  • Operating with 1 ground framing crew, 2 pole setting crews / rock boring, 1 Anchor testing crew, 1 steel pole assembly / erection crew.
  • Pole setting is at structure 155 working south
  • Ground framing at structure 86 working south
  • Preparing all stringing set-ups
  • Stringing OPGW rope and wire
  • Wire and OPGW is now completed to structure 559
  • Crew will commence stringing to substation from structure 1030 to structure 1080, once section is complete, return to structure 559 and continue stringing south.
  • Sagging conductor
  • Dead-Ending conductor
  • Clipping in conductor
  • Delivering travelers and materials to structures
  • Rock boring holes for pole setting on the 115 kV
  • Installing anchors on the 115 kV corridor
  • Installing rig mats in areas of concern
  • Installing Micro Pile Foundations on the 115 kV
  • Receiving 115 kV materials
  • Performing orientations for PowerTel employees and sub-contractors
  • Health and Safety team on site
  • Environmental team on site overseeing all construction activities, performing bird sweeps.
  • Have weekly meetings with White Feather Alex Peters and Elder Tom Quill.
  • Continue building of all-weather road to sub-station
  • Continue surveying along ROW's
  • Plan and organize for upcoming work activities
  • Hiring of more First Nations community members
  • Draco
  • Building all weather road to sub station
  • Floating PowerTel’s equipment
  • Supplying aggregate for pole foundations

Windigo/Expedition

  • Operating the man camp

FN Timber

  • Installing corduroy along swamp sections on the 115 kV corridor

EBS

  • Continue Micro Pile installation