Activities for the Week of August 19-25
PowerTel
- Operating with 1 ground framing crews, 2 pole setting crews/Rock boring, 1 Anchor testing crew, 1 Steel pole assembly/Erection crew
- Preparing all stringing set-ups
- Stringing OPGW rope and wire
- Sagging conductor
- Dead-Ending conductor
- Clipping in conductor
- Delivering travellers and materials to structures
- Rock boring holes for pole setting on the 115kV
- Installing anchors on the 115kV corridor
- Installing rig mats in areas of concern
- Installing Micro Pile Foundations on the 115kV
- Receiving 115kV materials
- Receiving poles for the 115kV
- Performing orientations for PowerTel employees and sub-contractors
- Health and Safety team on site
- Environmental team on site overseeing all construction activities
- Continue building of all-weather road to substation
- Plan and organize for upcoming work activities
- Hiring of more First Nations community members
EPTCON
- Mobilizing to site to begin substation civil work
Draco
- Building all weather road to substation
- Floating PowerTel’s equipment
- Supplying aggregate for pole foundations
Windigo/Expedition
- Operating the man camp
First Nation’s Timber
- Currently on turn around
EBS Geostructural Inc.
- Continue micro pile installation