Activities for the Week of August 19-25

PowerTel

  • Operating with 1 ground framing crews, 2 pole setting crews/Rock boring, 1 Anchor testing crew, 1 Steel pole assembly/Erection crew
  • Preparing all stringing set-ups
  • Stringing OPGW rope and wire
  • Sagging conductor
  • Dead-Ending conductor
  • Clipping in conductor
  • Delivering travellers and materials to structures
  • Rock boring holes for pole setting on the 115kV
  • Installing anchors on the 115kV corridor
  • Installing rig mats in areas of concern
  • Installing Micro Pile Foundations on the 115kV
  • Receiving 115kV materials
  • Receiving poles for the 115kV
  • Performing orientations for PowerTel employees and sub-contractors
  • Health and Safety team on site
  • Environmental team on site overseeing all construction activities
  • Continue building of all-weather road to substation
  • Plan and organize for upcoming work activities
  • Hiring of more First Nations community members

EPTCON

  • Mobilizing to site to begin substation civil work

Draco

  • Building all weather road to substation
  • Floating PowerTel’s equipment
  • Supplying aggregate for pole foundations

Windigo/Expedition

  • Operating the man camp

First Nation’s Timber

  • Currently on turn around

EBS Geostructural Inc.

  • Continue micro pile installation