Activities for the Week of July 1-7

PowerTel

  • Operating with 2 ground framing crews, 1 pole setting crew, one material delivery crew, 1 anchor testing crew, 1 Steel pole assembly / erection crew
  • Preparing all stringing set-ups
  • Commence both rope and wire stringing
  • Delivering travelers and materials to structures
  • Rock boring holes for pole setting on the 115 kV
  • Installing anchors on the 115 kV corridor
  • Installing rig mats in areas of concern
  • Installing Micro Pile Foundations on the 115 kV
  • Receiving 115 kV materials
  • Receiving poles for the 115 kV
  • Performing orientations for PowerTel employees and sub-contractors
  • Health and Safety team on site
  • Environmental team on site overseeing all construction activities, performing bird sweeps.  
  • Have weekly meetings with white feather Alex Peters and Elder Tom
  • Continue building of all-weather road to sub-station
  • Continue surveying along ROWs
  • Plan and organize for upcoming work activities
  • Hiring of more First Nations community members

Draco

  • Building all weather road to sub station
  • Floating PowerTel’s equipment
  • Windigo/Expedition
  • Operating the man camp

FN Timber

  • Removal of merchantable timber off of ROW

EBS

  • Continue Micro Pile installation