Activities for the Week of July 15-21

PowerTel

  • Operating with 2 ground framing crews, 2 pole setting crews, 1 material delivery crew, 1 Anchor Testing crew, 1 Steel pole assembly / erection crew
  • Preparing all stringing set-ups
  • Stringing OPGW rope and wire
  • Sagging conductor
  • Dead-Ending conductor
  • Clipping in conductor
  • Delivering travelers and materials to structures
  • Rock boring holes for pole setting on the 115 kV
  • Installing anchors on the 115 kV corridor
  • Installing rig mats in areas of concern
  • Installing Micro Pile Foundations on the 115 kV
  • Receiving 115 kV materials
  • Receiving poles for the 115 kV
  • Performing orientations for PowerTel employees and sub-contractors
  • Health and Safety team on site
  • Environmental team on site overseeing all construction activities, performing bird sweeps
  • Have weekly meetings with White Feather Alex Peters and Elder Tom
  • Continue building of all-weather road to sub-station
  • Continue surveying along ROWs
  • Plan and organize for upcoming work activities
  • Hiring of more First Nations community members

Draco

  • Building all weather road to sub station
  • Floating PowerTel’s equipment

Windigo/Expedition

  • Operating the man camp

FN Timber

  • Removal of merchantable timber off of ROW

EBS

  • Continue Micro Pile installation