Activities for the Week of July 8-14

PowerTel

  • Operating with two (2) ground framing crews, two (2) pole setting crews, one (1) material delivery crew, one (1) Anchor testing crew, One (1) Steel pole assembly & erection crew.
  • Preparing all stringing set-ups
  • Stringing both pulling rope and conductor
  • Sagging, Dead ending and clamping in conductor
  • Delivering travelers and materials to structures
  • Rock boring holes for pole setting on the 115 kV
  • Installing anchors on the 115 kV corridor
  • Installing timber mats in areas of concern
  • Installing Micro Pile Foundations on the 115 kV
  • Receiving 115 kV materials
  • Receiving poles for the 115 kV
  • Performing orientations for PowerTel employees and subcontractors
  • Health and Safety team on site
  • Environmental team on site overseeing all construction activities, performing bird sweeps.  
  • Have weekly meetings with Whitefeather Alex Peters and Elder Tom Quill.
  • Continue building of all-weather road to substation
  • Continue surveying along ROW
  • Plan and organize for upcoming work activities
  • Hiring of more First Nations community members

Draco

  • Building all weather road to substation
  • Floating PowerTel equipment
  • Windigo/Expedition
  • Operating the Camp

FN Timber

  • Removal of merchantable timber off of the Transmission Line ROW

EBS

  • Continue Micropile installation