Activities for the week of May 6-12

PowerTel

  • Receiving materials
  • Delivering materials to structure locations
  • Framing poles on 115kV section
  • Pole Setting on 115kV line along Taxi Bay Road and Nungesser Road
  • Equipment/Tool usage training
  • Performing orientations for PowerTel employees and sub-contractors
  • Health and Safety team on site
  • Environmental team on site
  • Have weekly meetings with Whitefeather's Alex Peters and Elder Tom

Whitefeather/Draco

  • Building all weather road to substation
  • Hauling PowerTel's equipment 
  • Equipment rentals to PowerTel

Windigo/Expedition

  • Operating the camp

Obish

  • Rock boring along 115kV corridor near Taxi Bay