Activities for the week of May 13-19

PowerTel

  • Continue setting poles on the 115 kV corridor along Nungesser Rd
  • Framing Poles
  • Delivering Davit arms to structure locations.
  • Aerial framing davit arms
  • Rock boring on the 115 kV corridor 
  • Receiving materials
  • Delivering poles on 115 kV Right of Way
  • Performing orientations for PowerTel employees and sub-contractors
  • Health and Safety team on site
  • Environmental team on site
  • Have weekly meetings with white feather Alex Peters and Elder Tom
  • Plan and organize for upcoming work activities

Whitefeather/Draco

  • Building road to substation
  • Hauling PowerTel's equipment 
  • Equipment rentals to PowerTel

Windigo/Expedition

  • Operating the camp

Obish

  • Rock boring along 115 kV corridor near Taxi Bay

EBS

  • Installing Micro-Piles on 115 kV corridor