Activities for the week of April 15-21

PowerTel

  • Rock boring on the 115kV section
  • Receiving 115kV materials
  • Receiving poles for 115kV
  • Delivering poles on 115kV line
  • Pole Setting on 115kV line along Taxi Bay Road
  • Cleaning and servicing all vehicles
  • Performing orientations for PowerTel employees and sub-contractors
  • Health and Safety team on site
  • Environmental team on site
  • Have weekly meetings with Whitefeather's Alex Peters and Elder Tom

Whitefeather/Draco

  • Building all weather road to substation
  • Hauling PowerTel's equipment 

Windigo/Expedition

  • Operating the camp

Obish

  • Rock boring along 115kV corridor near Taxi Bay