Activities for the week of March 11-18

PowerTel

  • Complete rock boring holes north of Berens River
  • Complete pole setting and framing poles on the 25kV north of Berens River
  • Complete Installing anchors on the 25kV section north of the Berens River
  • Complete stringing of 25kV section
  • Continue clamping in conductor on 25kV section
  • Working off of rig mats on south side of Berens River in order to clear Right of Way and construct 25kV Section
  • Installing Micro Pile Foundations on the 115kV Section
  • Receiving 115kV materials
  • Receiving poles for the 115kV Section
  • Delivering poles on 115kV section
  • Performing orientations for PowerTel employees and sub-contractors
  • Health and Safety team on site
  • Environmental team on site
  • Weekly meetings with white feather Alex Peters and Elder Tom
  • Commence building of all-weather road to sub-station
  • Continue surveying along Right of Way
  • Recruiting and hiring of First Nations community members

Whitefeather/Draco

  • Right of Way trail building on north side of the Berens River
  • Building all weather road to Substation
  • Hauling PowerTel's equipment
  • Leveling chip piles along Right of Way

Windigo/Expedition

  • Operating the camp 

Obish

  • Continue clearing on 115kV corridor
  • Rock boring on both 25kV and 115kV

W.E. Stone

  • Complete clearing Right of Way corridor from Pikangikum towards Berens River
  • Continue clearing on the 115kV corridor

FN Timber

  • Assist with Right of Way clearing on both 25kV and 115kV corridors