Activities for the Week of February 25 to March 4

PowerTel

  • Continue pole setting and framing poles on the 25kV section north of Berens River
  •  Rock boring holes for pole setting on the 25kV section north of Berens River
  • Installing anchors on the 25kV section north of the Berens River
  • Installing rig mats south of Berens River in order to clear Right of Way and construct 25kV Line
  • Installing Micro Pile Foundations on the 115kV Line
  • Receiving 115kV materials
  • Receiving stringing equipment
  • Commence stringing
  • Performing orientations for PowerTel employees and sub-contractors
  • Health and Safety team on site
  • Environmental team on site
  • Have weekly meetings with Whitefeather Alex Peters and Elder Tom
  • Commence building of all-weather road to sub-station

Windigo/Expedition

  • Operating the camp

Obish

  • Continue clearing on 115kV corridor

Draco

  • Building all weather road to substation
  • Right of Way trail building on north side of the Berens river
  • Placing rig mats on the south side of the Berens River
  • Hauling PowerTel's equipment

    W.E. Stone

    • Clearing Right of Way corridor from Pikangikum towards Berens River