Activities for the week of February 11-17

PowerTel

  • Receive/Haul equipment to Pikangikum
  • Receive/Deliver poles and material to 25kV section starting in Pikangikum 
  • Work with client on permanent road installation
  • Hold weekly meetings with White Feather
  • Continue orientations for contractors
  • Health and Safety team on site
  • Set Poles on 25kV section
  • Frame poles 25kV section
  • Clear Right of Way on 25kV section
  • People on site - 29 Staff plus union

Expedition/Windigo

  • Operating camp
  • People on site - 4

Obish

  • Continue clearing 115kV Right of Way along Nungesser Rd.
  • People on site – 15 - 17

Draco

  • Mulch 25kV Right of Way from Pikangikum working towards Berens River
  • Build Right of Way trail from Pikangikum towards Berens River
  • Build Right of Way trail and Access points along Nungesser Rd. (115kV)
  • Haul PowerTel's equipment
  • People on site – 4-6

W.E. Stone 

  • Mulch 25kV Right of Way alongside Draco
  • Clean up 115kV Right of Way along the Nungesser Rd.
  • Clear 25kV Right of Way from Pikangikum towards Berens River
  • People on site – 11

Hedberg/ERG

  • Returning this week in order to complete the Right of Way boundary flagging from structure 135 to the north side of the Berens River 
  • Flag permanent rd to substation
  • People on site – 2