Activities for the Week of November 4-10

PowerTel

  • Continuing minor deficiency work on the Grid Line  

  • Planning stages of re-closer installation north and south end  

  • Performing orientations for PowerTel employees and sub-contractors

  • Health and Safety team on site

  • Environmental team on site overseeing all construction activities  

  • Have weekly meetings with White Feather Alex Peters and Elder Tom

  • Plan and organize for upcoming work activities

  • Continue ROW remediation work

  • De-Mob equipment once completed

Draco

  • Floating PowerTel’s equipment

  • De-Mobbing equipment from site

Windigo/Expedition

  • Operating the man camp

EPTCON

  • Continue back fill up to ground grid elevation

  • Continue installation of below grade infrastructure

  • Install breakers

  • Install structural steel

  • Install bus work

  • Install transformers

  • Install grounding