Activities for the Week of November 18-24

PowerTel

  • Continuing minor deficiency work on the Grid Line  

  • Planning stages of re-closer installation north end 

  • Planning stages for the secondary service for the operation of the Re-Closer South end 

  • Final inspection on 25 kV line north of Berens river

  • Performing orientations for sub-contractors

  • Health and Safety team on site

  • Environmental team on site, overseeing all construction activities  

  • Have weekly meetings with White Feather Alex Peters and Elder Tom

  • Continue ROW remediation work

  • De-Mob equipment once completed with

  • Crew leaving site November 26th, returning to work December 5th

Draco

  • Floating PowerTel’s equipment

  • De-Mobbing equipment from site

Windigo/Expedition

  • Operating the man camp

EPTCON

  • Install secondary structures

  • Begin terminating cables

  • Transformer oil fill

  • Begin commissioning activities