Activities for the Week of November 11-17
PowerTel
Continuing minor deficiency work on the Grid Line
Planning stages of re-closer installation North and South end
Performing orientations for PowerTel employees and sub-contractors
Plan and organize for upcoming work activities
Continue ROW remediation work
De-Mob equipment once completed with
Windigo/Expedition
Operating the man camp
EPTCON
Station back fill
Electrical installation