Activities for the Week of October 7-13

PowerTel

  • Operating with 1 Anchor testing crew, 1 Steel pole assembly / erection crew.

  • Preparing all stringing set-ups

  • Stringing OPGW rope and wire

  • Sagging conductor

  • Dead-Ending conductor

  • Clipping in conductor

  • Delivering travelers and materials to structures

  • Receiving 115 kV materials

  • Performing orientations for PowerTel employees and sub-contractors

  • Health and Safety team on site

  • Environmental team on site overseeing all construction activities  

  • Have weekly meetings with White Feather Alex Peters and Elder Tom

  • Plan and organize for upcoming work activities

  • Commence ROW remediation work

Draco

  • Floating PowerTel’s equipment

  • Supplying aggregate for pole foundations

Windigo/Expedition

  • Operating the man camp

EPTCON

  • Continue formwork for the Transformer Foundation #1 center pcs, and Piers, one to one half day of Rebar

  • Continue to SOG for Transformer #2

  • Foundation SOG (Two CVT and Bus Bar SOG foundation needs to be completed)

  • EPTCON Electrical Crew will work at the Pole Area at the north area end

  • Grading and Backfilling with Granular A to level 348.15 level