Activities for the Week of September 30 – October 6

PowerTel

  • Operating with 1 Steel pole assembly / erection crew

  • Preparing all stringing set-ups

  • Stringing OPGW rope and wire

  • Sagging conductor

  • Dead-Ending conductor

  • Clipping in conductor

  • Delivering travelers and materials to structures

  • Installing rig mats

  • Receiving 115 kV materials

  • Performing orientations for PowerTel employees and subcontractors if necessary

  • Health and Safety team on site

  • Environmental team on site overseeing all construction activities 

Draco

  • Maintaining all weather road to substation

  • Floating PowerTel’s equipment if necessary

Windigo/Expedition

  • Operating the man camp

EPTCON

  • Continue substation civil construction with a focus on all of the foundation pours

Note: PowerTel’s first day of work for this rotation is Oct 3rd.