Activities for the Week of October 14-20

PowerTel

  • Operating with 1 Anchor testing crew and anchor installation crew

  • Installing extra ground rods where 20 Ohms or less have not been achieved

  • Installing rider poles at all road crossings

  • Preparing all stringing set-ups

  • Stringing OPGW rope and wire

  • Sagging conductor

  • Dead-Ending conductor

  • Clipping in conductor

  • Delivering travelers and materials to structures

  • Receiving 115kV materials

  • Performing orientations for PowerTel employees and subcontractors

  • Health and Safety team on site

  • Environmental team on site overseeing all construction activities  

  • Have weekly meetings with White Feather Alex Peters and Elder Tom

  • Plan and organize for upcoming work activities

  • Continue ROW remediation work

  • De-Mob equipment once completed with

Draco

  • Floating PowerTel’s equipment

  • Supplying aggregate for pole foundations

Windigo/Expedition

  • Operating the man camp

EPTCON

  • Pour Centre Pc of Transformer #2

  • Continue to Formwork the Walls for Transformer Foundation Walls.

  • Concrete Pour the SOG for the Bus Support Foundations Grid Line 2C

  • Dressing the Rebar for the Piers

  • Installation of the Pre-made Formworks for concrete work

  • Back-filling with Granular A around the exposed concrete and rest will be Granular B (General Back-filling) to FF elevations of 348.15