Activities for the Week of January 21-27th

PowerTel

  • Hand clearing 25Kv section in wet land areas
  • Packing swamps on 25Kv section
  • Float equipment across lake to 25Kv Mulch brush from community to Berens river
  • Stake 115Kv section from Structure #1 heading North
  • Monitor Right of Way clearing activities and ROW trail building

Obish

  • Proceeding north on 115Kv corridor with clearing
  • Chipping non-merchantable timber

W.E. Stone

  • Clearing 115Kv corridor along the all-weather road

Draco

  • Mulching 25Kv section from Pikangikum to Berens river
  • Right of Way trail building on both 25Kv and 115Kv ROW

Hedberg/ERG

  • No activity - On Turn Around

Expedition

  • Final touch ups at camp