December 11-16 Activities

This schedule is subject to change

Monday December 11

  • PowerTel reviewing environmentally sensitive areas
  • Crew renovating Stormer Lake Camp

Tuesday December 12

  • Orientation for Contractors
  • Crew renovating Stormer Lake Camp

Wednesday December 13

  • Commence flagging north side of Berens River starting in Pikangikum
  • If permit approved for camp, commence leveling of ground for camp at Winter Road and Nungesser Road
  • Crew renovating Stormer Lake Camp

Thursday December 14

  • Continue flagging north of Berens River
  • Continue ground work at camp
  • Crew renovating Stormer lake camp

Friday December 15

  • Continue Flagging north of Berens River
  • Continue ground work at man camp
  • Crew from Stormer lake traveling home
  • Tentatively commence line clearing north section of Right of Way

Saturday December 16

  • Continue flagging
  • Tentatively continue line clearing north section of Right of Way

*This schedule has been edited from the original post. Due to environmental constraints there will be no Right of Way work done south of the Berens River this week.