November 2017

  • Contract Signing

  • Initial Material Procurement

December 2017

  • Remaining Material Procurement

  • Mobilization and Site Setup

  • Right of Way Flagging and Clearing Begins

  •  Access Roads and Site Preparations Begin

January 2018

  • Construction of Line Foundations Commences

  • Material Receipt and Delivery Commences

  • Line Construction Commences

March 2018

  • Ongoing Construction

  • Right of Way Clearing Complete

  • Construction of Substation Commences

October 2018

  • Substation complete

November 2018

  • Line Construction Complete